An underlined date is a date you’ve set. A boldfaced and underlined date is a date
you’ve set than cannot be met.
When a date is beyond the limits of the application’s calendar (1973–2039), MacProject II displays question marks in place of the date.
-- part contents for card part 2
----- text -----
You see a boldfaced and underlined date.
-- part contents for background part 7
----- text -----
Verify that Show All is on in the Search menu, rather than Show Search. Show All is dimmed and has a check mark beside it when all project data is displayed.
If the date of the Time Now Line is set outside the time span of your project, it will not appear.
-- part contents for card part 3
----- text -----
Troubleshooting
-- part contents for card part 4
----- text -----
4 of 6
-- part contents for card part 5
----- text -----
You see “??” instead of a date.
-- part contents for card part 6
----- text -----
All tasks and milestones appear in the Schedule Chart but seem to be missing in other charts.